Schedule & Projects

Emergency Repair Projects Completed

  • 22 FHWA projects and 5 FEMA projects have been completed
  • 5 construction projects were able to include earthquake repairs
  • Notable emergency projects include:
    • Minnesota SE Off Ramp EM Repair 2018 Quake
    • Seward Hwy 36th to Tudor EM Repair 2018 Quake
    • Vine Rd MP 2.5 EM Repair 2018 Quake
    • Glenn Parks Interchange EM Repair 2018 Quake
    • Glenn Hwy Mirror Lk EM Repair 2018 Quake

Emergency Repair Projects Ongoing

  • Seward Hwy MP 50 – Nov 2018 EQ ER
  • Emergency Embankment & Drainage Repairs – Nov 2018 EQ ER

Construction 2020 FEMA Project Groupings

  • Willow-Fishhook Road 00027 – Nov 2018 EQ PR
  • Knik River Road, Palmer 00030 – Nov 2018 EQ PR
  • Clark-Wolverine Road 00031 – Nov 2018 EQ PR 
  • Old Matanuska Road 00032 – Nov 2018 EQ PR
  • Buffalo Mine Road – Nov 2018 EQ PR 
  • Old Rabbit Creek Road 00029 – Nov 2018 EQ PR
  • Clark-Wolverine Road and Huntley Road – Nov 2018 EQ PR
  • VFW Road, Eagle River 00065 – Nov 2018 EQ PR

Construction 2020 FHWA Project Groupings

  • Glenn Highway at Mirror Lake – Nov 2018 EQ PR
  • Glenn Highway MP 40-68 – Nov 2018 EQ PR
  • Glenn Parks Interchange Repairs – Nov 2018 EQ PR 
  • Central Region Bridges – Nov 2018 EQ PR
  • Anchorage District Group A – Nov 2018 EQ PR

Construction 2021 FHWA Project Groupings

  • Kenai Peninsula Area Repairs – Nov 2018 EQ PR
  • Mat-Su Area Pavement Repairs – Nov 2018 EQ PR
  • Anchorage District Group B – Nov 2018 EQ PR
  • Eagle River Bridge Repairs – Nov 2018 EQ PR
  • Mat-Su Borough Road Repairs – Nov 2018 EQ PR
  • AWWU: Briggs Pedestrian Tunnel Repairs – Nov 2018 EQ PR
  • MOA: Dowling – Nov 2018 EQ PR
  • MOA: 3rd Avenue & post Road – Nov 2018 EQ PR